Chelan awards airport waterline contract, will maintain traffic during construction

Posted

CHELAN – The Chelan City Council awarded a $3.64 million contract Nov. 10 to extend city water to the Chelan Municipal Airport, with construction scheduled to begin Feb. 1 and plans to keep at least one lane of traffic open during the work.

The award to Corridor Contractors LLC of Spokane came after the city rejected a competing bidder’s protest. Public Works Director Jake Youngren said favorable bids should allow a $6.5 million state grant to cover the project without drawing on additional funding committed by the city, Chelan County and the Chelan Douglas Regional Port Authority.

The project will extend a 16-inch water transmission main along Highway 97A to the airport. Substantial completion is expected by the end of May 2027, ahead of a deadline to recover state grant funds by the end of June.

Youngren said a full road closure no longer appeared advantageous enough to pursue. The current plan calls for maintaining at least one lane of travel, with flaggers directing alternating traffic through portions of the construction area.

Traffic control costs are included in the construction contract, he said. Councilmembers Tim Hollingsworth and Dan Boon encouraged staff to consider ways to reduce disruption and address concerns about traffic using alternate routes.

The project also prompted questions about whether nearby residents could eventually receive city water.

Howard Flat resident Reggie Collins told council he and others near the airport had hoped for years that the city would extend service to their area. He said he was disappointed to hear neighboring properties might not be allowed to connect.

“The individuals that are out there, including myself and our homes, we don’t have fire hydrant systems,” Collins said. “We don’t have potable water except for some wells and streams, and those cannot always be counted on.”

City Administrator Laura McAloon said serving properties outside city limits presents restrictions and offered to follow up with Collins. Staff clarified that the airport itself is within city limits.

Youngren said the city is interested in additional water users, but potential connections would require navigating jurisdictional boundaries and conditions attached to the city’s use of state highway right-of-way.

“And so we, we are looking for users,” Youngren said. “We definitely need demand on that line and are willing to look at creative ways to do that.”

He explained that the project is designed to transmit water to the airport area, where a distribution system could potentially be expanded, rather than provide numerous individual connections along the route.

The project also includes a smaller recirculation line and pumping equipment to keep water moving and maintain drinking water quality while demand remains limited.

The city opened three construction bids Nov. 5. Corridor’s bid, including sales tax, was $3,643,247.80. Selland Construction of Wenatchee bid $4,240,632.15, and Strider Construction bid $4,867,343.35.

Selland protested Corridor’s bid Nov. 6. Youngren said city staff, RH2 Engineering and City Attorney Quentin Batjer reviewed the protest and denied it Nov. 10, finding that the issues raised did not require rejecting the bid.

Batjer said the objections included missing initials on changes to bid documents and a zero-dollar entry for an item with no specified quantity. The city determined those issues did not affect the bid calculation or give Corridor an unfair advantage.

Hollingsworth questioned whether the substantially lower price could lead to additional costs during construction. Youngren said staff had reviewed the contractor’s qualifications, checked references and received favorable feedback. The qualifications included experience installing the type and size of pipe required for the project.

The city will not execute the contract before Nov. 16, Youngren said. That date marks the end of the required waiting period triggered after a bid protest is rejected.

In addition to the state grant administered by the Department of Commerce, the project has commitments of $666,000 each from the county and Port, along with approximately $840,000 allocated by the city. Youngren said those additional contributions are not currently expected to be needed.

He also cautioned that staff could return with proposals to expand the project’s scope while pricing and available funding are favorable.

Council approved the contract award unanimously.