PUD faces 88-week equipment wait as sourcing questions complicate projects

Posted

WENATCHEE – Buying equipment for Chelan PUD’s transmission system requires planning nearly two years ahead, and uncertainty over federal sourcing requirements is adding another complication.

Commissioners unanimously voted Nov. 16 to reject the lone bid for 115-kilovolt circuit breakers needed for several transmission projects and authorized staff to negotiate a purchase instead.

Manufacturers estimate an 88-week delivery time for the equipment, approximately 20 months, project manager Abra O’Leary told commissioners.

“So, we are trying to look ahead at the projects that we want to plan and prepare,” O’Leary said.

The purchase illustrates some of the challenges involved in building and maintaining electrical infrastructure: securing equipment far in advance, finding suppliers that can meet purchasing requirements and resolving contract terms before work proceeds.

In this case, price and delivery time were within the PUD’s expectations. O’Leary said the proposal fell within the engineer’s cost estimate and the anticipated 88-week lead time.

The problem was the bidder’s exceptions to the PUD’s supply-chain specifications and proposed price adjustment terms for additional optional units. Staff determined those departures made the bid nonresponsive, meaning it did not meet the solicitation’s requirements.

The PUD had already extended the original bid period before receiving the single proposal.

Commissioners’ decision allows staff to negotiate with suppliers rather than advertise for bids again. The resolution cited time constraints and project requirements as reasons for taking that approach.

Federal sourcing rules are also affecting suppliers’ willingness to commit, staff told the board.

An executive order issued Aug. 26 directs the U.S. Department of Energy to address national security risks involving foreign-supplied equipment used in the nation’s bulk-power system. High-voltage circuit breakers are among the equipment covered by the order’s definitions.

The order authorizes restrictions when specified foreign-entity connections and security risks are identified. DOE guidance says it does not prohibit all foreign-produced equipment.

At the meeting, PUD staff said more than one prospective bidder had reported being unable to obtain commitments from component suppliers because of uncertainty surrounding the order.

Staff expected additional federal direction in December and identified Dec. 24 as an anticipated milestone.

O’Leary said the PUD could begin examining where critical components originate and negotiate with multiple parties while awaiting that direction. Staff said some contract terms would need to remain unresolved until the requirements became clearer.

Asked whether the situation jeopardized project timelines, staff said it did not.

The discussion also prompted questions about whether the PUD’s bidding requirements were contributing to unsuccessful solicitations.

Staff said commissioners now see a greater concentration of purchasing problems because routine contracts can proceed under delegated authority. Purchases requiring exceptions, including authorization to negotiate after rejecting a bid, still come before the board.

Most solicitations proceed without those issues, staff said, while purchasing and project teams review problematic bids for lessons they can apply to future purchases.

O’Leary said experience buying circuit breakers for the Basalt substation would help inform the negotiations.

“We do have a strong negotiation starting point with the engineer’s estimate and the time frame,” she said.