MALAGA – A plan to retire two older Malaga Water District wells and bring another into service is moving forward with Microsoft funding, following months of water-quality concerns and questions from residents about when the change would happen.
The Chelan Douglas Regional Port Authority approved $472,766 in additional engineering work Nov. 10, covering both the proposed well improvements and engineering associated with a separate pipeline project. Microsoft would pay for the work through its existing development and reimbursement agreement with the Port.
Stacie de Mestre, the Port’s director of economic development and capital projects, said staff identified room within that agreement’s funding as one of the final major pipeline projects went out to bid. At the water district’s request, they approached Microsoft about adding the decommissioning of wells 1 and 2 and outfitting well 6.
“This would help improve water quality and just further build up the Malaga Water District system,” de Mestre said.
Microsoft agreed to the additional work, provided it fits within the agreement’s remaining funds.
The proposal follows discussions at water district meetings about replacing the older sources. District minutes record Commissioner Mike Schoenwald proposing June 1 that wells 1 and 2 be decommissioned and well 6 brought online instead. The proposal appeared under a discussion of PFOS, one of the substances in the broader PFAS family. These are often referred to as “forever chemicals,” as they don’t break down easily in the environment.
Residents also sought information about the change. Sharon Seal asked July 6 about the decommissioning timeline and whether there would be a public meeting. Jon Port raised the issue again Aug. 17.
Water-quality concerns have included nitrates as well as PFOS. In a Dec. 20, 2024, letter, RH2 Engineering reported that nitrate concentrations in wells 1 and 2 had trended upward since 2012, with recent samples exceeding 5 milligrams per liter. Levels in wells 5 and 6 ranged from 2.5 to 3.1 milligrams per liter. The maximum contaminant level for nitrates is 10 milligrams per liter, according to the letter.
Microsoft does not add PFOS during its cooling process.
The proposed work at well 6 is separate from the addition of wells 7 and 8. The district’s Sept. 21 minutes reported that those two wells were already supplying the system and that Microsoft was interested in helping outfit well 6 after the West Malaga loop project.
The engineering authorization approved Nov. 10 includes design and construction administration for the well work, along with additional engineering time spent evaluating the final pipeline route.
De Mestre said staff explored several routes, including alternatives that would have required easements from 12 property owners, before settling on a route mostly within existing right of way.
“But that exercise of determining the route did incur or use quite a bit of engineering time,” she said.
The amendment brings RH2’s total authorization for that engineering task to $5,169,571. That figure represents the engineering authorization, rather than the total construction cost of the water improvements.
The Port will still need to amend its interlocal agreement with the water district and its development and reimbursement agreement with Microsoft. De Mestre said staff want better construction estimates before completing those changes.
The work would also be subject to the Port’s 5% administrative fee. RH2 bills for time incurred, although de Mestre said she expected the additional engineering authorization would be used.
For the water district, the action advances a proposed change in supply that has been discussed for months. Construction costs and a completion schedule for the added well projects were not provided during the Port presentation.